Construction of Road K46 (P79/1) Phase 2

Department of Roads and Transport 2022/06/22 - 22:00


Construction of Road K46 (P79/1) Phase 2 between PWV 5 and N14 (P158/2) (Diepsloot)

Contract duration is 16 months. The project was disrupted and works suspended until resumption in February 2022. It is estimated to be completed by the end of the year.

The road construction is located in Diepsloot in the Fourways area, north of Johannesburg. Construction commenced at Erling Road Interchange adjoining Phase 1 at km 7.5 and continuing in the north direction ending a km 13.8 after the N14.

K46 follows the existing alignment with deviation in certain areas due to geometric constraints. The project when complete will improve traffic capacity in the North-South direction between the N1 and N14.